University of Gothenburg

Information about construction work week

Should there be changes in the planning, we will publish information about this.

Please respect the demarcation of the work area!

New working hours: weekdays 07.00 - 23.00. The project have a permit to perform weekend work but will only use this if necessary.

An explanation of the different work steps and what type of noise they cause can be found further down. There you also find estimated disturbances in different parts of the School.

Planned work:

Week 51 (16 – 20 December)

  • Concrete work, vaults and walls (disturbance level, medium)
  • Concrete work, shelter (disturbance level, medium)
  • Excavation at building E for upcoming connection with building F (disturbance level, medium)
  • Removal of props (steel pipes) level 3 and 2 (disturbance level, low)

Week 52 (23 – 27 December):

  • Limited maintenance work (disturbance level, low)

Week 1 (1 – 3 January):

  • Preliminary drilling of RD piles in connection with building E (disturbance level, high)

Week 2 (7 – 10 January):

  • Steel assembly in the deep excavation, lift shafts, hanging bridges, etc. (disturbance level, low)
  • Excavation at building E for upcoming connection with building F (disturbance level, medium)
  • Concrete work, walls (disturbance level, medium)
  • Removal of props (steel pipes) level 3 and 2 (disturbance level, low)

Week 3 (13 – 17 January):

  • Concrete work, vaults (disturbance level, medium)
  • Concrete work, walls (disturbance level, medium)
  • Removal of props (steel pipes) level 3 and 2 (disturbance level, low)
  • Excavation at building E for upcoming connection with building F (disturbance level, medium)
  • Dismantling of scaffolding at the small crane (disturbance level, low)

Planned works September 2024 – February 2025

The project is progressing towards the ground surface, and by February – March 2025, it is planned to have cast the floor slab one level above the ground surface.

As the casting progresses upwards, Isobetong is filled between the sheet piling and the concrete structure. This is done to transfer the ground pressure to the permanent concrete structure. The props (the round tubes that keep the sheet pile walls apart) hold the pressure until the concrete can replace them. The removal of the props will begin at the end of 2024.

September:

  • Concrete casting in the deep excavation
  • Backfilling between sheet piling and concrete structure
  • Concrete works in the shallow section

October:

  • Concrete casting in the deep section
  • Concrete castings in the shallow section
  • Prefabricated assembly of stairs and floor slabs

November:

  • Concrete casting in the deep section
  • Concrete castings in the shallow section
  • Concrete floor slab at ground level in the deep section

December:

  • Concrete casting in the deep section
  • Concrete castings in the shallow section
  • Removal of beams

January 2025:

  • Concrete casting in the deep section
  • Concrete castings in the shallow section
  • Removal of beams

February 2025:

  • Concrete casting in the deep section
  • Concrete castings in the shallow section
  • Removal of beams

Estimated degree of disturbance in different parts of the school.

Green = low
Yellow = medium
Red = high

Image
Illustration of disturbances from the construction work in different parts of the School
Photo: Akademiska Hus

 

Explanation of technical terms and level of disturbance:

 

Excavation work

Involves excavation and removal of soil and clay (normal machine noise, beating sound when clay is shaken from the scoop).
Medium level of noise

 

 

If you have questions

Questions about ongoing construction work that are affecting your work:

Campus Service Haga, service.handels@gu.se, 031 786 2160

Questions about the project at large:

Emil Gurbani, Project manager, Strategic Project Management, University of Gothenburg, emil.gurbani@gu.se, +46 76 61 85 208

Questions and wishes regarding the communication about the project:

Maria Norrström, Director of Communications, School of Business, Economics and Law, maria.norrstrom@handels.gu.se , 031-783 1247, 0709-226689